4.5.1 Failure of any sample. Should any one item of a special
sampling fail to meet any of the specified test requirements,
acceptance of the product shall be suspended by the Government until
necessary corrections to all production since the last test as well
as to current production has been accomplished in accordance with
the provisions of the contract.
4.6
Inspection equipment.
4.6.1 Government-furnished inspection equipment. where the
contract provides for Government-furnished test equipment, supply
and maintenance of test equipment shall be in accordance with the
applicable requirements of MIL-I-45607.
4.6.2
Contractorfurnished inspection equipment.
4.6.2.1 Government design. Unless otherwise specified in the
contract, all inspection equipment identified by drawing number in
specifications or QAPs forming a part of the contract shall be
supplied by the contractor in accordance with the design specified.
The contractor may, however, propose alternatives to Government
designs for approval in accordance with 6.3.
4.6.2.2 Contractor design. The contractor shall design and
supply inspection equipment compatible with the "Methods of
Inspection" specified in 4.7 of the specification and with the
component inspection procedures specified in "Examination" and "Test
Facilities" requirements of MIL-F-13926 whenever Government designs
are not specified (see 4.6.2.1). Since tolerance of test equipment
is normally considered to be within 10 percent of the product
tolerance for which it is intended, this inherent error in the test
equipment design must be considered as part of the prescribed
product tolerance limit. Thus , concept, construction, materials,
dimensions, and tolerances used in the design of test equipment
shall be so selected and controlled as to ensure that the test
equipment will reliably indicate acceptability of a product which
does not exceed 90 percent of the prescribed tolerance limit and
permit positive rejection when nonconforming. Construction shall be
such as to facilitate routine calibration of test equipment.
Contractor inspection equipment designs shall be submitted for
approval in accordance with 6.3.
4.6.2.3 Test equipment. In conjunction with 4.6.2.1 and
4.6.2.2, the test equipment listed in Table V shall be used in the
performance of the applicable test methods and procedures as
specified in 4.7.