MIL-G-50351A (AR)
4.5 Special samp ling.
One fine pulse delay assembly out of
the first 50 produced and one out of each 100 produced thereafter
shall be selected at random. The sample shall have met the
requirements and tests in Table II and shall then meet the
requirements and tests in Table III. Unless otherwise specified
in the contract, the items shall be returned to the lot upon
successful completion of testing.
TABLE III.
Special sampling.
4.5.1 Failure of sample.
Should any one item of a special
sampling fail to meet any of the specified test requirements,
acceptance of the product shall be suspended by the Government
until necessary corrections to all production since the last
test, as well as to current production has been accomplished in
accordance with the provisions of the contract.
4.6
Inspection
equ ipment.
4.6.1 Government-furnished inspection equipment. Where the
contract provides for Gove rnment-furnished test equipment, supply
and maintenance of test equipment shall be in accordance with the
applicable requirements of MIL-I-45607.
4.6.2
Contractor-furnished
inspection
equipment.
4.6.2.1 Government design. Unless otherwise specified in
the contract, all inspection equipment identified by drawing
number in specifications or QAPs forming a part of the contract
shall be supplied by the contractor in accordance with design
The contractor may, however, propose alternatives to
specified.
Government designs for approval in accordance with 6.3.
9